1 year 3 months ago #6364 by marco64io
If I right understood BPMN specifications, in an ad-hoc sub-process I can put more task without control flow among them and I cannot put start and end events. Well, if in Modelio 4.1.0 I create, in a BPMN process diagram, an ad-hoc subprocess and in the diagram of this subprocess I put two tasks without control flow, I get three errors in model audit: a rule R3080 violation for each task and a rule R3250 violation for the subprocess, that seems in contradiction with BPMN specifications. Is this a bug or I'm doing something wrong?

Please Log in or Create an account to join the conversation.

1 year 3 months ago #6365 by phv
Hi Marco,

Seems that you understood BPMN specifications perfectly well;)

The current implementation of rules R3080 and R3250 of Modelio is obviously too strict forbidding anything to be created in the 'adhoc' task.
Right now you should be able to disable these rules: right click on the error and disable in the menu.

However, we file a bug report for this issue to be corrected in the future.

Modelio Team.
PhV

Please Log in or Create an account to join the conversation.

1 year 3 months ago #6366 by marco64io
Perfect! Thanks!